The Dunstable High Street Regeneration Phase 2 Improvements scheme has transformed the High Street environment within the centre of Dunstable by widening and decluttering footways, improving the street scene and wayfinding (phase 2) as well as reallocating the carriageway and installing an extensive system of sustainable urban drainage (phase 3). Car movements have been de-prioritised in favour of pedestrians, cyclists and users of public transport services as well as creating a more attractive and vibrant High Street for residents, visitors and businesses.
Funding Stream: Local Growth Fund (LGF)
LGF Awarded: £2.5m
Total Project Cost: £5.26m
Project Status: Completed June 2021
Projected Outputs: 81 new direct jobs, 80 new homes, 89% occupancy rate, £18.7m GVA impact over 5 years
Website: https://www.centralbedfordshire.gov.uk/info/68/dunstable/19/dunstable_-_giving_back_your_high_street/4