Houghton Brook Flood Storage Area Case Study

Join over 10,000 organisations who’ve used the Growth Hub’s free business support

This project has built a flood storage area to mitigate future flooding in Luton, protecting 643 residential and non-residential properties along the Houghton Brook and River Lea, infrastructure and access routes in Luton (A6 and the Luton-Dunstable Busway).

Funding Stream: Local Growth Fund (LGF)
LGF Awarded: £1m
Total Project Cost: £5.7m
Project Status: Project completed February 2021
Projected Outputs: GVA impact of £53.43m over the next 10 years through flood mitigation impact. £35 million in economic benefits associated with the reduction in flood risk for 643 residential and commercial properties.

March 2021

Houghton Brook Flood Storage Area in Luton now completed

A new £8.5 million flood storage area to benefit 600 residential and commercial properties, along with key infrastructure, in Luton has been completed.

STAY CONNECTED: SIGN UP TO OUR NEWSLETTER

Never miss an opportunity to apply for funding, or attend an event by receiving the latest news and updates straight to your inbox.

Our newsletter drops monthly; to be included, simply add your email address.